Project Description

Rehabilitation of three street façades, replacement community facilities and specific structural reinforcements.

For the painting of the facade and the recovery of false windows, glazing was used based on silicates Keim house.

The budget gap was due to the decision to change the gas and project changes as indications of the heritage building’s department of the City.

The building has been involved in:

  • Rehabilitation of façades with the recovery of the original drawing of false windows and reconstructing missing mezzanine floor balconies.
  • Replacing the aluminum door with a new one made of glass and rusted steel.
  • Replacing the old plumbing with deposits full installation of running water and adequate battery in the lobby of the building.
  • Complete replacement and adjustment of the gas from street to each house key. The counters were centralized in the deck.
  • Installation of telecommunications and electricity ladder.
  • Cover relocation and adjustment to each household, the individual air conditioning installation.
  • Timely Reinforcement wooden beam heads.
  • Termites anti entire wood structure by placing boxes cellulose impregnated with poison. This work was done by the specialized company Ibertrac.

Project Overview: ASSAONADORS 35

Actions:
       Rehabilitation of three street façades, replacement community facilities and specific structural reinforcements.
Promotor: Owners Community
  Localización: No. Assaonadors street. 35, Barcelona
Project and technical management: ARQ Fòrum SL
Initial Budget: 153.305,60 €
Budget force closure: 176.001,50 €
Touch area: 782,00 m²